Hughes/Raytheon Facility
PROJECT: Hughes/Raytheon Facility – Fullerton, California
CLIENT: SunCal Properties
CONTRACT AMOUNT: $6,200,000

Environmental Remediation and Total Demolition Overview
The Hughes/Raytheon project consisted of asbestos abatement, demolition, and site clearing of 34 industrial manufacturing buildings. The project scope included:
- Asbestos abatement, demolition, and site clearing of 270 acres (approximately 2.5 million square feet of buildings)
- Asbestos abatement of 600,000 square feet of roofing, 15,000 linear feet of pipe insulation, 500,000 square feet of floor tiles, 1,000 linear feet of window caulking, and 8,000 square feet of boiler insulation
- Removal of PCB, Mercury, CFC, and other hazardous materials
Resources and Equipment:
- 8 excavators
- 4 track loaders
- 3 rock trucks
- 40 laborer crew
CST Environmental recycled metal, wood, and concrete, and our company also processed and stockpiled approximately 200,000 tons of concrete and asphalt for crushing into a base product for owner’s use.