Geneva Steel Mill

PROJECT: Geneva Steel Mill – Vineyard, Utah
CLIENT: Anderson Geneva Development Inc.
CONTRACT AMOUNT: $53,000,000

  • Geneva Steel Mill
  • Geneva Steel Mill
  • Geneva Steel Mill
  • Geneva Steel Mill
Charlotte Colisesum
Charlotte Colisesum
Charlotte Colisesum
Geneva Steel Mill

 

 

 

 

 

 

 

 

 

 

 

Environmental Remediation and Total Demolition Overview
The Geneva Steel Mill project involved the demolition, asbestos abatement, and hazardous materials remediation of an idle steel mill. The work included:

CST Environmental was able to recycle 80 miles of railroad ties and track, 400 rail carts, and 13 locomotives. Several large machines and equipment were salvaged, and CST Environmental cleaned and removed more than 400 tanks. Over 300,000 tons of material was recycled.

CST Environmental overcame the challenge of the project size by using large Hitachi 1200 and 1100 excavators, in-place shears, and 80-ton hall pack trucks. Work was completed in 30 months utilizing 40 to 50 laborers and operators. CST Environmental is the only contractor that was able to perform all facets of demolition and environmental abatement of an integrated steel plant.